
![Clay TABLE 1: SOIL WEIGHT AND VOL CHANGE CHARACTERISTICS Unit Weight [ib/cu yd (kg/m°)] Swell Shrinkage Load Shrinkage Loose](https://media.cheggcdn.com/media/513/513388af-a4c2-4252-8dad-d3e6610cde5e/phprBo74g.png)




Expert Answer
CommentHi,
Solution as follows:
1. Load factor
From Table 1,
Load factor for clay (L) = 0.77
2. Bucket fill factor
From Table 2,
Bucket fill factor for hard clay (F) = 0.65 to 0.95
Average value of (F) = 0.80
3. Swing depth factor
Given Data:
· Depth of excavation = 5 ft
· Maximum Digging Depth = 16 ft
· Angle of swing = 85 deg
% Depth of cut = 5/16 = 0.31 = 31%
From Table 3,
Swing depth factor for 30% depth and 75⁰ = 1.21
Swing depth factor for 30% depth and 90⁰ = 1.15
Swing depth factor for 30% depth and 85⁰ (S) = 1.19
4. Cycles per hour
From Table 4,
Cycles per hour for hard clay with medium excavator (n) = 130
5. Adjustment factor
From table 5,

6. Productivity
Given Data:
· Heaped capacity of bucket (C) = 2 CY
· Efficiency E = 85%
Production in BCY per hour can be calculated by below formula:

Hope the same is clear. In case of any clarifications, please leave comment in comments section.
Please give us a good rating, if you are satisfied with the response.
How would you rate our reply?
Best Regards
Chegg Expert Team

![sof volume - section areax Length (: Swell - 254] V =(1.2 X15) X305x1.25 -686-254CM Spor Bank Sizes: ½ 올 BE La came] t-anR 48](https://media.cheggcdn.com/coop/889/889baf19-224b-4d27-9e39-3fa92e76d22f/1615564734570_2021_03_129_28PMOfficeLens.jpg)

ليست هناك تعليقات:
إرسال تعليق