2. A medium hydraulic excavator will be used to dig a trench in hard clay. The minimum trench size is 36 in. wide with an aveClay TABLE 1: SOIL WEIGHT AND VOL CHANGE CHARACTERISTICS Unit Weight [ib/cu yd (kg/m°)] Swell Shrinkage Load Shrinkage LooseTABLE 2: BFF FOR EXCAVATORS Material Bucket Fill Factor Common earth, loam Sand and gravel Hard clay Wet clay Rock, well-blasTABLE 3 SWING-DEPTH FACTOR FOR BACKHOES Depth of Cut Angle of Swing (deg) (% of Maximum) 45 60 75 90 120 180 1.33 1.21 1.08 3TABLE 4 STANDARD CYCLES/HR FOR HYDRAULIC EXCAVATORS Machine Size Wheel Small Excavator: Medium Excavator Type of Material TraTABLE 5 ADJUSTMENT FACTOR FOR TRENCH PRODUCTION Type of Material Adjustment Factor 0.60-0.70 Loose (sand, gravel, loam) Avera

Show transcribed image text

Expert Answerinformation icon

  • Anonymous's Avatar

    Hi,

    Solution as follows:

    1. Load factor

    From Table 1,

    Load factor for clay (L) = 0.77

    2. Bucket fill factor

    From Table 2,

    Bucket fill factor for hard clay (F) = 0.65 to 0.95

    Average value of (F) = 0.80

    3. Swing depth factor

    Given Data:

    · Depth of excavation = 5 ft

    · Maximum Digging Depth = 16 ft

    · Angle of swing = 85 deg

    % Depth of cut = 5/16 = 0.31 = 31%

    From Table 3,

    Swing depth factor for 30% depth and 75⁰ = 1.21

    Swing depth factor for 30% depth and 90⁰ = 1.15

    Swing depth factor for 30% depth and 85⁰ (S) = 1.19

    4. Cycles per hour

    From Table 4,

    Cycles per hour for hard clay with medium excavator (n) = 130

    5. Adjustment factor

    From table 5,

    (0.95 +1.00) Average adjustment factor for firm plastic soils(A) = 2 0.975

    6. Productivity

    Given Data:

    · Heaped capacity of bucket (C) = 2 CY

    · Efficiency E = 85%

    Production in BCY per hour can be calculated by below formula:

    85 P = C x ExLXF1S X X 4 = 2x x 0.77 x 0.80 x 1.19 x 130 x 0.975 = 157.95 BCY/hr 100

    Hope the same is clear. In case of any clarifications, please leave comment in comments section.

    Please give us a good rating, if you are satisfied with the response.

    How would you rate our reply?

    Best Regards

    Chegg Expert Team

    Comment 

A 1000-ft (305-m)-long pipeline requires an excavation 4 ft (1.2 m) wide to an aver- age depth of 5 ft (1.5 m). If the soil is dry common earth, what size spoil bank will be created by the excavation?

Show transcribed image text

Expert Answerinformation icon

  • Anonymous's Avatar

ليست هناك تعليقات:

إرسال تعليق

ahmad alhayek تصميم ahmad alhayek جميع الحقوق محفوظة 2016

صور المظاهر بواسطة sndr. يتم التشغيل بواسطة Blogger.